Our Projects

A typical list of the housing societies we've powered across Thane, Mumbai, Navi Mumbai and Kalyan, part of 3,500+ installations in Maharashtra.

20+
Housing societies powered
918 kWp
Installed for these societies
200 kWp
Largest single society project
57 days
Work order to net meter (200 kWp)
Case study · Dosti Imperia, Thane
200 kWp

Two wings, Corona A and Corona B (100 kWp each), powering lifts, water pumps and staircase lighting.

1 Jan 2026Work order issued
26 Feb 2026Net meter commissioned

200 kWp for Dosti Corona, Dosti Imperia

Dosti Corona invited tenders from 10 reputed vendors and chose Spacefire Corp. We managed all MSEDCL coordination (name change, load addition, feasibility, release letter and meter installation) and completed the project more than a month ahead of schedule, in time for the summer sun.

57 daysOrder to net meter
1 month+Ahead of schedule
20 daysSubsidy credited after commissioning
10Vendors evaluated
Start your society's project
Housing society clients

Housing society projects

May 2026Housing society
25 kWp

Amar Vaishali CHSL

Naupada, Thane

Completed 25 May 20262 months
Mar 2026Housing society
20 kWp

A3 Vikas Complex CHSL

Utharsar, Thane West

Completed 06 Mar 20262 months
Feb 2026Housing society
200 kWp

Dosti Corona, Dosti Imperia

Manpada, Thane

Completed 26 Feb 202657 days
Jan 2026Housing society
7 kWp

Shri Krishna Deep CHSL

Shirgaon, Badlapur East

Completed 20 Jan 20261 month
Dec 2025Housing society
100 kWp

Dosti Ornata, Dosti Imperia

Manpada, Thane

Completed 31 Dec 20253 months
Dec 2025Housing society
15 kWp

Krishnai CHSL

Parsik Nagar, Kalwa

Completed 22 Dec 20253 months
Dec 2025Housing society
12 kWp

Tulip CHSL

Khadakpada, Kalyan West

Completed 22 Dec 20253 months
Oct 2025Housing society
50 kWp

Bhoskar CHSL

Airoli, Navi Mumbai

Completed 01 Oct 20252 months
Sep 2025Housing society
30 kWp

A4-A5 Vikas Complex CHS

Utharsar, Thane West

Completed 15 Sep 20252 months
Sep 2025Housing society
15 kWp

Akash CHSL

Nerul, Navi Mumbai

Completed 01 Sep 20253 months
Jul 2025Housing society
100 kWp

Siddhachal Phase III CHSL

Vasant Vihar, Thane

Completed 03 Jul 20253 months
Feb 2025Housing society
15 kWp

Aditya CHSL

Mulund East, Mumbai

Completed 28 Feb 20252 months
Apr 2024Housing society
33 kWp

Platinum Venecia CHS Ltd

Nerul, Navi Mumbai

Completed 30 Apr 20243 months
Apr 2024Housing society
21 kWp

Gopaldeep CHS Ltd

Mulund East, Mumbai

Completed 30 Apr 20242 months
Apr 2024Housing society
40 kWp

Gagangiri CHS Ltd

Mulund East, Mumbai

Completed 10 Apr 20243 months
Jan 2023Housing society
10 kWp

Guruprasad CHS Ltd

Seawoods, Navi Mumbai

Completed 15 Jan 20232 months
Jan 2023Housing society
24 kWp

Shree Swami Prasad CHSL

Khadakpada, Kalyan West

Completed 15 Jan 20232 months
Dec 2022Housing society
31 kWp

Ramdas CHS Ltd

Naupada, Thane

Completed 31 Dec 20221 month
Mar 2022Housing society
50 kWp

Bella Vista CHS Ltd

Majiwada, Thane

Completed 11 Mar 20223 months
Jul 2019Housing society
120 kWp

Indraprastha Sankul CHSL

Khadakpada, Kalyan West

Completed 20 Jul 20192 months
Design

3D layout designs

Before installation we prepare a 3D layout of the building to plan panel placement around water tanks, lift rooms and shadow areas.

3D solar layout design for Sai Heritage, Mulund

Sai Heritage, Mulund

3D solar layout design for Rose Tower, Virar

Rose Tower, Virar

3D solar layout design for Siddhachal Phase 2, Thane

Siddhachal Phase 2, Thane

3D solar layout design for Sai Heritage, Mulund (view 2)

Sai Heritage, Mulund (view 2)

3D solar layout design for Siddhachal Phase 2, Thane (view 2)

Siddhachal Phase 2, Thane (view 2)

3D solar layout design for B3 Vikas Complex: three layout options

B3 Vikas Complex: three layout options

Drone video: Bella Vista CHS, Thane (50 kWp)

2 min
Free site survey

Planning solar for your society?

Get a free site survey, an optimum capacity recommendation and a clear RoI analysis for your building.